Woodland Lakes, Thirsk

Supply and install of KS1000SRW sinusoidal profiled composite panels to the roof and wall cladding areas.

Paragon Cladding Services supplied and installed KS1000SRW sinusoidal profiled composite panels to the roof and wall cladding areas of this leisure facility in Thirsk. Clad areas included high humidity swimming pool environment and roofs which were laid to pitches of 20 degrees. Roof panels were installed as 15mr single length roof panels using a crane mounted suction system, a design decision which assisted with the speed of erection but also improved the integrity of the roof by removing unnecessary end laps. The projecting arrow head feature above the entrance was completely sealed using a cold applied GRP weathering system between the rake cut roof panels and perimeter feature fascia; similar raking details were also incorporated to various wall areas to provide a stunning finish to a beautiful building.